Section 1
The time available has reduced by 25 percent which reflects a decrease by one month in the time available for preparation and conducting the wedding. The project which was to be concluded in June must now be concluded in May. The time lines for each activity must, therefore, be readjusted in line with the new time deadline. Everything must be concluded within Three months and not the original four Months The budget has increased by 12 percent. This represents an increase of $1800. The total amount of money available for expenditure is, therefore, $ 16800. The budgetary allocations for each Continue reading...